[E4] Between Tohoku Expressway Tsukidate IC and Ichinoseki IC
Implementation of face-to-face traffic control throughout the day due to renewal work

-Efforts to ensure long-term safe use of aging Expressway

E4 Tohoku Expressway Tsukidate IC and Ichinoseki IC
Due to renewal work Face-to-face traffic control throughout the day Carry out

Renewal

September 11, 2018
East Nippon Expressway Co., Ltd.
Tohoku Regional Head Office Sendai Management Office

NEXCO EAST Sendai Management Office (Sendai City, Miyagi Prefecture)E4 Tohoku Expressway Tsukidate IC and Ichinoseki IC, face-to-face traffic control will be enforced from October 10 (Wednesday) due to the floor plate replacement work of the dilapidated Sansakogawabashi . If you use this section, please make further efforts to drive safely and make sure you have enough time to go when you use it.

In addition, we are working to shorten the construction period, such as using precast products produced in the factory in advance, When the construction period is postponed (use a spare day) due to bad weather, etc. Tohoku Expressway Between Ichinoseki IC and Wakayanagi Kinari IC (In-bound), the maximum distance is 1km between 15:00 and 18:00 on November 25 (approx. 5 minutes), and between Tsukidate IC and Wakayanagi Kanari IC (Out-bound), November 23. A maximum of about 2km between 9:00 and 15:00 (passage time +10 minutes) and about 1km at 16:00 on the 25th (passage time +5 minutes) Is predicting congestion. Customers who are planning to use ICs near the regulated section on November 23 and 25, who are predicting the occurrence of traffic congestion, ask for the cooperation of the detour, such as avoiding the traffic congestion prediction section. I will do it. On other days, we do not predict the occurrence of traffic congestion.

During construction Homepage for construction , Or traffic information will be posted on websites such as "DraTra", so please check when using the Expressway.

It is necessary work to keep highway network function sound for a long time. We will do our best to minimize inconveniences to our customers, so please understand and cooperate.

Construction image photograph
  • [Removal of old slabs]
    [Removal of old slabs]
  • [New slab installation status]
    [New slab installation status]
  • [Restrictions on face-to-face traffic]
    [Restrictions on face-to-face traffic]
  • The photo is an example of floor slab replacement work on the Sakogawa Bridge (In-bound line) that was constructed in the spring of 2018.

1 Traffic regulation section

Tohoku Expressway Tsukidate IC-Ichinoseki IC (upper and lower lines)

Traffic regulation section

2 Traffic regulation period and congestion forecast

(1) Traffic regulation period

Wednesday, October 10, 2018-Thursday, December 6, 2018 (58 days)

Traffic regulation period
(2) Congestion prediction

When the construction period is postponed (use a spare day) due to bad weather, etc. , As below, we predict traffic jams on holidays.

  • Congestion Forecast
  • Construction section map
(3) Request for detour

Customers who are planning to use ICs near the regulated section on November 23 and 25, who are predicting the occurrence of traffic congestion, ask for the cooperation of the detour, such as avoiding the traffic congestion prediction section. I will do it.

  • [1] If you are planning to get off at Wakanagi Kinari IC (In-bound line), please consider getting off at Ichinoseki IC, which is one front.
  • [2] Customers planning to enter from the Ichinoseki IC (In-bound line), please consider entering from the Wakayanagi Kanari IC one step ahead. [ Route guidance 1 Refer to]
  • [3] Customers who plan to get off at Wakanagi Kinari IC (Out-bound line), please consider getting off at the Tsukidate IC, which is one step ahead.
  • [4] Customers planning to enter from the Tsukidate IC (Out-bound line), please consider entering from the Wakayanagi Kanari IC, which is one step ahead. [ Route information 2 Refer to]
Route information 1 (Route from Ichinoseki IC to Wakanagi Kinari IC)
Route information 1 (Route from Ichinoseki IC to Wakanagi Kinari IC)
Route Information 2 (Route from the Tsukidate IC to the Wakayanagi Kinari IC)
Route Information 2 (Route from the Tsukidate IC to the Wakayanagi Kinari IC)

3 Traffic restrictions

In the floor slab replacement work, we will reduce the section of each two lanes of up and down lines to one lane and consolidate it on one side to enforce face-to-face traffic all day. During the several days at the beginning and end of the construction period, there will be an all-day lane restriction for up and down lanes as a preparatory work to switch lanes. *About the construction regulation step diagram Attachment-1 [PDF:274KB]Link to PDFPlease refer to.

Image of face-to-face traffic regulation
Image of face-to-face traffic regulation

4 Construction content

About 40 years have passed since the opening of the Sansakogawa Bridge between Tsukidate IC and Wakayanagi Kanari IC on the Tohoku Expressway cracks caused by repeated wheel loading due to the increase in size of the vehicle, salt content of the antifreezing agent sprayed during the winter As a result, concrete floor slabs have deteriorated and reinforcing bars have rusted, so it is necessary to implement drastic measures against deterioration.

By replacing the deteriorated existing concrete slab with a new slab, it will be reborn as an Expressway that can be used safely and comfortably.

Construction overview
Construction overview
  • A floor slab is a structural member that directly supports an automobile or the like passing through a bridge and transmits the load to the girder.

5 Requests for use

  • [1] The construction section will be restricted to face-to-face traffic throughout the day for approximately 3.0 km. Since the current number of lanes on each side will be reduced to 2 lanes, please try to drive more safely and make sure you have enough time to travel. Also, Because a spare day may be used due to bad weather etc. , For customers who are planning to use the construction section on November 23 and 25, when traffic congestion is predicted, we would appreciate your cooperation in changing the IC used.
  • [2] Since the driving lane and shoulder are narrow in the face-to-face traffic restricted section, observe the regulated speed when traveling, secure the distance between the vehicles, and pay sufficient attention to rear-end collisions. In addition, the lane changes greatly before and after the face-to-face traffic restricted section, so please follow the local information signs and so on.
  • [3] There are vehicles coming and going around the construction site, so please be careful and pass ahead.
  • [4] During the construction period, we will provide construction regulation information using road information boards and road signs and call for caution to drive safely. Before riding, please check the above information before riding safely.
  • [5] Please check the latest traffic restrictions and traffic congestion information on websites such as "DraTra" before going out.
Image of information provision image around the construction site
Image of information provision image around the construction site

6 Efforts to minimize inconvenience to customers due to construction work

Use of precast products for shortening the construction period and improving quality

By adopting precast products for floor slabs and wall balustrades, we have shortened the construction period compared to usual and shortened the regulation period to the maximum. * Precast is a product manufactured in advance at a factory.

Construction flow for precast wall balustrade

Construction flow for precast wall balustrade

Source: DAK precast wall balustrade method study group

Strengthening of information provision

In addition to the information board (electric bulletin board) on the Expressway, the regulation plan will be announced in advance in the Tohoku region through TV commercials, radio commercials, and newspaper advertisements.・ Post a leaflet.

Information image * Publicity material for the renewal work that was carried out in the spring of 2018
  • ◆ TV commercial
    TV commercial
  • ◆ Stand sign
    Standing sign
  • ◆ Poster
    Posters
  • ◆ Leaflet
    Leaflet
Expressway information such as traffic congestion

NEXCO EAST Road Traffic Information Site "DraTra" provides real-time traffic information.
[PC]
[Mobile] http://m.drivetraffic.jp/

Display example of real-time traffic information

Display example of real-time traffic information

7 How to obtain road traffic information

(1) Road traffic information available before going out
  • NEXCO EAST Home Page " Construction regulation information (Provides information on construction regulations in each area)
    For Miyagi Prefecture, please see "Minami Tohoku".
  • NEXCO EAST Road Traffic Information Site "DraTra" (provides national Expressway traffic information)
    [PC]External link: Open in a new window
    [Mobile] http://m.drivetraffic.jp/
  • ハイウェイテレホン
    5分毎に更新される高速道路の交通最新情報をハイウェイテレホン(自動音声)で24時間提供しています。
    仙台局 022-711-1620
    (携帯電話・PHS短縮ダイヤル#8162)
  • NEXCO東日本お客さまセンター(24時間オペレーターが対応します。)
    0570-024-024 または 03-5338-7524
  • (公財)日本道路交通情報センター(JARTIC)の道路交通情報
    050-3369-6761(東北地方・高速情報)
    インターネットExternal link: Open in a new window
(2) Road traffic information available during driving
  • Road information board
  • Highway radio (AM1620kHz)
    Highway radio sections are indicated by signs on the Expressway.
  • Highway Information Terminal
    Wide-area road traffic information is reported on the monitor screens installed at SA and PA.
*Twitter official account "NEXCO East Japan (Tohoku)" (@e_nexco_tohokuExternal link: Open in a new window) Also distributes information.
Expressway renewal project
Expressway Renewal project
Now, bring safety and security to the next generation.
NEXCO EAST is dedicated to providing you with safety and security.
We will work on Expressway 's large-scale renewal and repair business.
URL: http://www.e-nexco.co.jp/renewal/External link: Open in a new window