Notice on Construction Regulations on the Do-O Expressway (between Toyoura IC and Noboribetsu Muroran IC)

-Implementation of "night closure"-

  • Corporate Top
  • Press Room
  • Press Release Hokkaido office
  • Notice on Construction Regulations on the Do-O Expressway (between Toyoura IC and Noboribetsu Muroran IC)

April 18, 2008
East Nippon Expressway Co., Ltd.
Hokkaido Regional Head Office

NEXCO EAST Hokkaido Regional Head Office (Sapporo City Atsubetsu-ku, Regional Head Office president: Katsuji Kubotera), between Do-O Expressway Toyoura Interchange (IC) and Noboribetsu Muroran IC, to ensure safe and comfortable traffic and reduce annual traffic restrictions, Please be informed that we will carry out "night closure" as follows. We apologize for the inconvenience, but we appreciate your understanding and cooperation.

In the case of rain, it will be postponed the next day (excluding Saturdays and Sundays), so please check the Japan Road Traffic Information Center, highway telephones, information boards, etc. for traffic restrictions.

1 Construction content and construction period

1. "Night traffic"
It is a closed road for pavement repair work, tunnel interior work, road marking work, tunnel cleaning, tunnel equipment work, tunnel inspection, etc.

【section】
(1) Toyoura IC-Date IC (upper and lower lines)
(2) Date IC-Noboribetsu Muroran IC (upper and lower lines)

【period】
(1) May 8 (Thursday) 20:00 to 6:00 the next morning (1 night)
[Preliminary day: Friday, May 9 from 20:00 to 6:00 the next morning]
May 12 (Mon), May 13 (Tue) 20:00 to 6:00 the next morning (2 nights)
[Preliminary days: May 14 (Wednesday) to May 16 (Friday) 20:00 to 6:00 the next morning]
(2) May 19th (Mon)-May 23rd (Fri) 20:00 to the next morning 6:00 (5 nights)
[Preliminary days: Monday, May 26th to Friday, May 30th from 20:00 to 6:00 the next morning]
* Postponed during bad weather, except at night on Saturdays and Sundays.

"Construction period calendar"

Image images from May 8th (Thu) 20:00 to the next morning 6:00, May 19th (Mon) to May 23th (Fri) 20:00 to the next morning 6:00

2 Detour

Please detour to general national highways No. 36, 37 and other roads when you are closed.

3 Regarding connection fare adjustment due to "night closure"

Because of road closures due to this construction, Do-O Expressway temporarily flow out, to bypass the general road, the customer is to be Noritsuga in the same direction again, "to give you in the transfer certificate issued IC Expressway ride closures Please receive the certificate of succession. After you transfer at an IC that has specified inflow again within 24 hours, if you hand over the "Expressway suspension connection certificate" when you first pay the fare, the toll will be changed according to the section you are using. We will make adjustments. The ICs that issue transit certificates and the ICs that have been designated to re-enter are as follows.

Customers who use ETC do not need to receive the "Expressway suspension connection certificate". Please use the same ETC card once before and after transit, and use ETC wireless communication with both the certificate issuing IC and the re-inflow designated IC.

"Certificate issuing IC, re-inflow designated IC"

Closed section, date and timeTransit certificate issuing ICRe-inflow designated IC
Toyoura IC ⇔ Date IC
May 8, May 12, May 13
20:00 - 6:00
  • Toyoura IC (direction Sapporo)
  • Abuta Toyako IC (Both directions)
  • Date IC (Yakumo direction)
  • Date IC, Muroran IC (direction Sapporo)
  • Toyoura IC, Chomanbe IC (direction Yakumo)
Date IC ⇔ Noboribetsu Muroran IC
May 19-May 23
20:00 - 6:00
  • Date IC (Sapporo direction)
  • Muroran IC (both directions)
  • Noboribetsu Muroran IC (Yakumo direction)
  • Noboribetsu Muroran IC, Noboribetsu East IC (Sapporo direction)
  • Date IC, Abuta Toyako IC (Yakumo direction)

The certificate is valid only if you transfer at the re-inflow designated IC within 24 hours after the issuance.
Please drive safely according to the information board, regulatory signs and guides.

4 Information during the construction period

 工事規制情報は、下記の各種媒体を通じて提供しております。

1.Internet

  • For the latest regulatory information, see DraTra "Please refer to the.
  • "Road Traffic Information Now! ! ] [ http://www.jartic.or.jp/ ]
  • "Highway road closure information (Hokkaido area)" *For mobile phones only
    Image of http://hokkaido.e-nexco.co.jp/[Http://hokkaido.e-nexco.co.jp/]

2. Flyers, posters
It is distributed and posted at Expressway service areas, parking areas, toll gate offices, NEXCO EAST Hokkaido Regional Head Office Muroran Administration Office, etc.

3. Telephone

  • "NEXCO EAST Customer Center"
    We will answer various inquiries regarding Expressway 24 hours a day, 365 days a year.
    Telephone Number
    0570-024-024(PHS・IP電話のお客さま:03-5338-7524
  • "Highway Telephone"
    We provide real-time traffic information (5 minutes update) 24 hours a day.
    Telephone Number
    011-896-1620(札幌)
    0166-54-1620(旭川)
    0143-59-1620(室蘭)
    0155-42-1620(帯広)
    (注)おかけ間違いのないようにご注意ください。
  • "Japan Road Traffic Information Center"
    We provide the latest traffic information.
    Telephone Number
    011-891-8111(午前7時~午後7時)

4. Road traffic information available while driving

  • Road information board
  • Highway radio (1620kHz)