-Efforts to ensure long-term use of aging Expressway

[E4] Between Tohoku Expressway Hanamaki IC and Morioka Minami IC
Implementation of face-to-face traffic control throughout the day due to renewal work

  • Corporate Top
  • Press Room
  • Press Release Tohoku office
  • [E4] Tohoku Expressway Hanamaki IC-Morioka Minami IC renewal construction enforces face-to-face traffic all day

The latest regulatory information isDraTraPlease see.

Image image of Expressway renewal project logo

September 2, 2020
East Nippon Expressway Co., Ltd.
Tohoku Regional Head Office Morioka Management Office

NEXCO EAST Morioka Management Office (Morioka City, Iwate Prefecture) E4 Tohoku Expressway At the Takina River Bridge located between the Hanamaki Interchange (IC) and the Morioka Minami IC, to replace the deteriorated reinforced concrete floor slab with a new floor slab We will reduce the section of each two lanes to one lane and implement face-to-face traffic regulation that consolidates on one side from Wednesday, September 23 all day.
The construction will reduce the number of lanes that can be driven from 2 lanes to 1 lane, so Tohoku Expressway Congestion is expected near the construction site between Hanamaki IC and Morioka Minami IC.
We apologize for the inconvenience, but if you drive in this section, please try to drive more safely and make sure you have enough time to travel.
Expressway This is a necessary construction to keep the network function healthy for a long time. We will do our best to minimize inconvenience to our customers, and we ask for your understanding and cooperation.

♦Construction image photograph

[Old floor slab removal status] photo
[Removal of old slabs]
[New floor slab installation status] photo
[New slab installation status]
[Surface traffic regulation status] photo
[Restrictions on face-to-face traffic]

1. Traffic regulation section

Tohoku Expressway Hanamaki IC-Morioka Minami IC (upper and lower lines)

Image of restricted traffic section Tohoku Expressway Hanamaki IC-Morioka Minami IC (upper and lower lines)

2. Traffic regulation period

September 23 (Wednesday) to November 12 (Thursday) 2020 (51 days) Preliminary day Including 7 days

Image of traffic regulation period (September 2020)
Image of traffic regulation period (October 2020 October)
Image of traffic regulation period (November 2020)
Image of traffic regulation period (color frame description of calendar)
  • We will also work on Saturdays, Sundays, and holidays.
  • The work may be postponed in bad weather.
  • The lane regulation date and the two-way traffic regulation date may change depending on the progress of construction.

3. Traffic restrictions

In the floor slab replacement work, we will reduce the section of each two lanes of up and down lines to one lane and consolidate it on one side to enforce face-to-face traffic all day long. For the first few days at the start and end of the construction period, both the upper and lower lanes will be regulated all day as preparation work for switching lanes.
*Please refer to the attached document [PDF:354KB] for the construction regulation step diagram.

♦ Two-way traffic regulation image

Image of lane regulation
Image of face-to-face traffic regulation

Four. Construction content

About 43 years have passed since the Takina River Bridge located between the Hanamaki IC and the Morioka Minami IC on the Tohoku Expressway (upper and lower lines) has passed. Deterioration of concrete slabs and rust on the reinforcing bars are caused by the salt content of the anti-freezing agent spraying, so it is necessary to implement drastic measures against deterioration.
By replacing the deteriorated existing concrete slab with a new slab, it will be reborn as a safe and comfortable Expressway.

♦ Construction overview

Image image of construction outline

Five. Request when using

  1. The construction section will be restricted to face-to-face traffic throughout the day for a maximum of approximately 3 km. It may be reduced from the current two lanes to one lane on one side, and congestion may occur at the construction site at the beginning, so please take time to go out.
  2. Since the driving lanes and shoulders are narrow in the two-way traffic regulation section, please observe the regulation speed when traveling and secure a sufficient distance between vehicles to be careful of rear-end collisions. In addition, the lanes change significantly before and after the two-way traffic regulation section, so please follow the local signs.
  3. Vehicles for construction work may enter and leave the area around the construction site, so please be careful when traveling ahead.
  4. During the construction period, we will provide traffic congestion information using simple information boards, construction regulation information using road information boards and road signs, and call for caution to drive safely. Please check this information when riding and drive safely.

♦ Image of information provided around the construction site

[Simple information board] photo
[Simple information board]
[Road information board] photo
[Road information board]
[Construction control material] photo
[Construction regulation materials]
  • The photo shows information provided by the Tohoku Regional Head Office.

6. Efforts to minimize inconvenience to customers due to construction work

[Adopting precast products to shorten the construction period and improve quality]

By adopting a precast PC floor slab, the construction period is shortened compared to usual, and the regulation period is shortened to the maximum.
*Precast is a product manufactured in advance at a factory.

[Installation of additional information signs for Shiwa IC]

♦ Additional guidance sign image

◆Image image of additional guidance sign

Shiwa IC can be used during the construction work for both the upper and lower lines. In order to prevent accidentally passing through the exit of Shiwa IC, additional guide signs will be installed on the Out-bound line in addition to the normal exit guide signs. When using the Shiwa IC, please check the guide signs and drive carefully.

[Advance notification of construction regulations and traffic congestion information through TV commercials, radio commercials, newspaper advertisements, etc.]

We will inform you in advance about the regulations by TV commercials, radio commercials and newspaper advertisements, mainly in the Tohoku region.

[Information image]

* 2020 Publicity material for the renewal work that was carried out in the spring.

♦ TV commercial

◆ Image of TV commercial

♦Standing sign

◆ Image of standing sign

♦ Poster

◆ Poster image

♦ Leaflet

◆ Image of leaflet

7. How to obtain road traffic information

(1) Road traffic information available before going out

  • NEXCO東日本お客さまセンター(24時間オペレーターが対応します。)
    0570-024-024 または 03-5308-2424
  • NEXCO EAST road traffic information site "DraTra" (provides national Expressway traffic information)
    [PC] https://www.drivetraffic.jp/
    [Mobile] http://m.drivetraffic.jp/
  • ハイウェイテレホン
    5分毎に更新される高速道路の交通最新情報をハイウェイテレホン(自動音声)で24時間提供しています。
    盛岡局 019-639-1620
    (携帯電話・PHS短縮ダイヤル #8162
  • (公財)日本道路交通情報センター(JARTIC)の道路交通情報
    050-3369-6603(岩手情報)
    050-3369-6761(東北地方高速情報)
    インターネット http://www.jartic.or.jp/

(2) Road traffic information available during driving

  • Road information board
  • Highway radio (AM1620kHz)
    The section on the highway radio is indicated by the signs on the Expressway.
  • Highway information terminal
    Wide area road traffic information is provided on the monitor screens installed in SA/PA.
  • Official Twitter account "NEXCO EAST (Tohoku)" ( @e_nexco_tohoku ) Also delivers information.

Image image of Expressway renewal project logo

Expressway renewal project

Safety and security for the next generation.
NEXCO EAST will work on large-scale renewal and repair business of Expressway in order to provide you with safety and security.