Construction contract for changes in wages etc. due to the Great East Japan Earthquake
Operation of contract

February 24, 2012

NEXCO EAST will operate the construction contract contract Article 25, Paragraph 6 as follows in order to deal with the rapid fluctuation of wages etc. in the area particularly affected by the Great East Japan Earthquake, as follows: .

1 Target construction

The applicable construction work is subject to the following.

Construction carried out in Iwate, Miyagi and Fukushima prefectures

Construction with a remaining work period of two months or more when requesting a change consultation (referred to as "slide consultation") in Article 25, Paragraph 6 of the contract

2 Timing of billing

If there is a change in wage level, you can make a claim before the next change in wage level.

Whenever the wage level changes, you can request a slide consultation each time.

3 Method of calculating the amount of change (slide amount) in the contract amount

The amount of change in contract amount due to changes in wage level or price level is one-hundredth of the amount of change amount related to the construction less the contract amount corresponding to the workable part on the base date. The amount exceeds the equivalent amount.

Both the orderer and the contractor will confirm the finished part on the reference date.

4 Handling of target construction under contract

NEXCO EAST 's contract manager will notify you of the contracted works under contract.