Regarding the continuation of special measures (Large use) of prepayment for construction

April 1, 2020
East Nippon Expressway Co., Ltd.

NEXCO EAST in, 2020 special measures of advance payments also ordered construction work in the degree of (Shito Large will continue).

Eligible down payments

March from 28 April 1 to 3, March 31, 2008 Ryowa, in prepayments to work to conclude a new contract, 2020 Ryowa 3, March 31, 2008 from April 1, What is paid out by

Details of Large use

Large the use of the prepayment and include the expenses required for the construction work, such as site management expenses and general management expenses.

(Note 1)
The maximum amount of the prepayment to be allocated to these is 25/100 of the prepayment amount.
(Note 2)
This special measure can also be applied to works for which a contract has already been concluded.
In that case, you need to change the contract contract, so please consult the contract department in charge of the contract.