About review of low bid price survey standard in construction
- Corporate Top
- Press Room
- Press Release Headquarters
- About review of low bid price survey standard in construction
November 25, 2008
East Nippon Expressway Co., Ltd.
NEXCO EAST is pleased to inform you that we have reviewed the criteria for low bid price survey for construction work to be ordered as follows.
調査基準価格の算定方法
The method of calculating the survey reference price is reviewed as shown in the figure below.

However, if the total amount exceeds 8.5/10 of the contract limit price, the amount of 8.5/10 is used, and if it is less than 2/3, the amount of 2/3 is used as the survey standard. Price and
Date of application
It will be applied from the construction of bids after December 1, 2008.