December 12, 2013
East Nippon Expressway Co., Ltd.
Hokkaido Regional Head Office

NEXCO EAST Hokkaido Regional Head Office (Sapporo-shi Atsubetsu-ku) is responsible for emergency work for road level difference near N87.0KP (Ebe Otomachi, Takigawa City) between Doki Do-O Expressway Takigawa Interchange (IC) and Fukagawa Junction (JCT) (Asahikawa direction). I will inform you that it was completed today at 14:00.

In addition, emergency work was carried out today by removing the road closures at 7 am when it was confirmed that driving in the overtaking lane was safe, and by restricting lanes.

We deeply apologize for any inconvenience caused by the long-term emergency construction.

1 Road closure status

Road name direction section Start date and time Release date and time
Do-O Expressway Asahikawa direction Takigawa IC ⇒ Fukagawa JCT 12/11 9:00 12/12 7:00

2 Damage situation

There are 2 steps with a length of about 10 m and 2 points with a length of about 2 m on the main road from the shoulder to the driving lane, and the maximum step is about 15 cm.

Image of damage situation