  • Ken-O Road Okegawa of Kitamoto review the opening goal of the inter-IC ~ Shiraoka irises IC.

November 30, 2010
Ministry of Land, Infrastructure, Transport and Tourism Kanto Regional Development Bureau Omiya National Highway Office
East Nippon Expressway Co., Ltd.
Kanto Regional Head Office Saitama Construction Office

Ken-O Road Okegawa Kitamoto IC and Shiraoka Shobu IC on the Ken-O Expressway, there is some difficult land construction due to the difficulty of land use, etc. Therefore, it is necessary to consider the service in 2012. I was just there.

I have been scrutinizing the business process so far, The situation that there is no prospect of acquisition at some sites Therefore, in the future, in parallel with the voluntary acquisition of land, there is no choice but to consider application of the land acquisition law. The land acquisition procedure is expected to take about two years at the earliest, so at this time, Opening target is after 2014 Is expected to become.

 具体的な供用時期については、今後の事業進捗や予算の状況を踏まえ検討して参ります。

We will continue to make our utmost efforts for early service.

Route outline

National highway No. 468 Ken-o Expressway (commonly known as Ken-O Road) is a motorway with an extension of about 300km planned to be located at a radius of 40-60km from the city center. By connecting, the traffic to the city center will be dispersed and traffic congestion will be alleviated.

Moreover, the opening from Okegawa Kitamoto IC to Kuki Shiraoka JCT, Ken-O Road by Kan-Etsu Expressway and Tohoku Expressway will be is connected, already opened to have Chuo and Kan-Etsu Expressway coupled with a section of more wide-area convenience Is expected to improve.

The progress status of the project in this section (land progress is as of the end of October, area basis) is as follows.

● Between Okegawa Kitamoto IC and Shiraoka Iris IC (extension 10.8km)

Land acquisition rate About 86% Has become Land acquisition and construction Is in progress.

Image of Large map of wide area map