(8th report)
About the situation of the Expressway with the earthquake centering on the Hamadori district in Fukushima Prefecture
- Corporate Top
- Press Room
- Press Release Tohoku office
- (8th report) About the condition of the Expressway accompanying the earthquake with the epicenter of Fukushima Prefecture Hamadori district
April 12, 2011
As of 16:45
East Nippon Expressway Co., Ltd.
Tohoku Regional Head Office
At NEXCO East Japan Tohoku Regional Head Office (Aoba Ward, Sendai City), earthquakes occurred at 17:16 on April 11, 2011 and at 14:07 on April 12, 2011, with the epicenter in the Hamadori region of Fukushima Prefecture. In response to this, we closed the lines and sections where there was a lot of shaking, carried out an emergency inspection, and released the road closures sequentially from the sections where safety was confirmed.
1. Section where suspension of traffic has been released
| Road name | section | By vertical line | Remarks |
| Ban-Etsu Expressway | Iwaki Sanwa IC-Ono IC | Up and down | 16:45 Cancellation of suspension of traffic |
2. Closed section (Tohoku Regional Head Office Office)
| Road name | section | By vertical line | Remarks |
| Ban-Etsu Expressway | Iwaki JCT-Iwaki Sanwa IC | Up and down | |
| Joban Expressway | Iwaki Nakoso IC-Iwaki Shikura IC | Up and down | |
| Joban Expressway | Iwaki Shikura IC-Joban Tomioka IC | Up and down | Because of the evacuation area of the nuclear power plant, traffic will be closed from March 11. |
- The latest information is DraTra, Information including general national highways JARTIC Please check with.
3. Major damages currently confirmed (Tohoku Regional Head Office Office)
| Road name | section | By vertical line | Damage situation |
| Joban Expressway | Iwaki Nakoso IC-Iwaki Yumoto IC | Up and down | Out-bound slope cut slope reaches In-bound line |
4. Current work status
The collapsed rock mass is being split into small pieces and is being carried out.
[Location map, etc.]



[Collapse situation photo]
The situation where the collapsed rock block covers the entire Out-bound line
(From the In-bound line, take Iwaki Yumoto behind and head towards Iwaki Nakoso in the early morning of April 12)
[Approximate collapse]
Extension: (Road direction): About 50m
Width: (road sideways): About 15m
Road deposit height: About 8m
Height of slope collapse: approx. 35 m
The situation where the collapsed rock block covers the entire Out-bound line
(From the Out-bound line, take Iwaki Yumoto behind and head towards Iwaki Nakoso in the early morning of April 12)
[Work status photo]
Carrying out work situation from the bottom end of the rock in sequence (from the In-bound line,
Iwaki Yumoto behind and headed towards Iwaki Nakoso at around 8:30 on April 12