Apology for communication service interruption due to cable damage in some areas of Ichikawa City, Chiba Prefecture

February 17, 2015
East Nippon Expressway Co., Ltd.
Kanto Regional Head Office

Due to NEXCO EAST ordering work on the Gaikan Expressway, the NTT communication cable was cut, and in some areas of Ichikawa City, Chiba Prefecture, communication and telephone calls became unavailable.

All communication and communication interruptions were restored at approximately 15:10 on Tuesday, February 17.

We deeply apologize to everyone who caused a great deal of inconvenience and trouble, and will work to prevent a recurrence.

1 Overview

At 8:30 pm, Monday, February 16, 2015, buried underground under construction of a well for the construction of Owada construction on the Gaikan Expressway, which was being carried out near 2-15 Higashi Owada, Ichikawa City, Chiba Prefecture. I disconnected the provided NTT communication cable, and now I can no longer use communication and calls in some areas of Ichikawa City.

2 Outage period

Monday, February 16, 2015, around 8:30 to Tuesday, February 17, around 15:10

3 Construction builder

Construction of Owada on the Gaikan Expressway
Shimizu Construction Co., Ltd., Maeda Construction Co., Ltd., Toyo Construction Co., Ltd.

4 Recurrence prevention

We will make every effort to prevent recurrence by making improvements such as prior confirmation of underground buried objects.