-Efforts to ensure long-term use of aging Expressway

[E4] Tohoku Expressway Nihonmatsu IC-Fukushima Iizaka IC renewal construction enforced face-to-face traffic all day

  • Corporate Top
  • Press Room
  • Press Release Tohoku office
  • [E4] Tohoku Expressway Nihonmatsu IC-Fukushima Iizaka IC Between-day traffic restrictions due to renewal work
Image of Renewal

On the weekend Congestion of up to 20 km, more than 1 hour to pass of
Since it is predicted to occur, please cooperate with detours, etc.

Oct. 2, 2018
East Nippon Expressway Co., Ltd.
Tohoku Regional Head Office Fukushima Management Office

NEXCO EAST Fukushima Management Office (Fukushima City, Fukushima Prefecture) E4 Tohoku Expressway At Omorigawabashi and Matsuzukagawabashi, which are located between Nihonmatsu IC and Fukushima Iizaka IC, replace old reinforced concrete slabs with new slabs. Due to construction work, we will reduce the section of each two lanes of up and down lanes to one lane and implement face-to-face traffic regulation that consolidates on one side from Saturday, October 20 to the whole day.

Construction from reducing the number of available traffic lane from two lanes to one lane, Tohoku Expressway of In the vicinity between Nihonmatsu IC ~ Fukushima Iizaka IC, In-bound up to about 20 km (transit time approximately 1 hour 50 minutes) in the line, Out-bound up to about 12km in line (1 hour 10 minutes transit time) Is predicting congestion.

We apologize for the inconvenience, but if you drive in this section, we will make further efforts to drive safely, and when you use the vehicle, please be sure to leave enough time to go. Also, For customers who are planning to use the construction section on the day when heavy traffic congestion is predicted, for customers who are planning to use the detour to the Joban Expressway, use of the Expressway via the general road, and interchanges used ( Please change your IC) or use public transportation.

 Tohoku Expressway Renewal Construction (Fukushima) Official Website during the construction period
[ http://www.e-nexco.co.jp/renewal/touhokudou/fukushima/ ] Will provide traffic information such as real-time traffic congestion time and recommended detours.
Please check this when using the Expressway.

Expressway This is necessary work to keep the network function sound for a long time. We will work to minimize inconvenience to our customers, so we appreciate your understanding and cooperation.

Image of the old slab removal situation
[Removal of old slabs]
Image of new floor slab installation
[New slab installation status]
Image of face-to-face traffic regulation
[Restrictions on face-to-face traffic]

1 Traffic regulation section

Tohoku Expressway Nihonmatsu IC-Fukushima Iizaka IC (upper and lower lines)

Image of traffic regulation section

2 Traffic restriction period and traffic congestion forecast

  • Traffic regulation period
    Tuesday, October 16, 2018 to Thursday, November 29, 2018 (45 days)
    Image of traffic regulation period
    • We will also work on weekends and holidays.
    • Work may be postponed in bad weather.
    • The face-to-face traffic regulation date may change depending on the progress of construction.
  • Traffic jam prediction
    During the construction period, on weekends Congestion of up to 20 km, more than 1 hour to pass Is predicting.
    Image of traffic jam forecast calendar
  • Request for detour
    During the regulation due to this construction, long traffic congestion (up to about 20km on the In-bound line and up to 12km on the Out-bound line) is predicted, beginning at the construction site. For customers who plan to use the construction section on the day of particularly heavy traffic congestion forecast, for customers who are planning to use the detour to Joban Expressway or use Expressway via general road, use IC Please change the number and use public transportation.
    • [1] Customers traveling from Fukushima City to the south of Fukushima City using the Fukushima Nishi IC and Fukushima Iizaka IC, Use Nihonmatsu IC to the south of Fukushima city, Customers who use the Nihonmatsu IC to go north from Fukushima City, To the north of Fukushima City using the Fukushima Nishi IC Please go out. (Refer to [1] Detour using general road)
    • [2] Customers using the Tohoku Expressway from the north of Sendai to the Iwaki City of Fukushima Prefecture and the Kanto region, or from the Kanto region to the north of Sendai, Please cooperate with the detour using the Joban Expressway.(Refer to [2] Detour route using Joban Expressway)
      [1] Image of detour using general road
      [2] Image of detour using the Joban Expressway
  • [2] route in the Joban Expressway if it is diverted to, because there is a section in which you plan to nighttime traffic stop on weekdays, "before going out DraTra such as" Website (traffic regulation information) Please check and confirm that you are ready to go.

We provide real-time traffic congestion time and recommended detours!

During the construction period, you can check real-time traffic congestion transit times and recommended detours on your PC or smartphone.

QR code

3 Traffic restrictions

In the floor slab replacement work, we will reduce the section of each two lanes of up and down lines to one lane and consolidate it on one side to enforce face-to-face traffic all day. For the first few days at the start and end of the construction period, both the upper and lower lanes will be regulated all day as preparatory work to switch lanes. * For the construction regulation step diagram Attachment [PDF: 166KB] Please refer to.

Image of face-to-face traffic regulation

Image of face-to-face traffic regulation

4 Construction details

About 40 years have passed since the opening of the Omorigawa Bridge and Matsuzukagawa Bridge between the Tohoku Expressway Nihonmatsu IC and Fukushima Iizaka IC (upper and lower lines). Since the salt content of the anti-freezing agent sprayed on causes the deterioration of concrete floor slabs and rust on the reinforcing bars, it is necessary to implement drastic measures against deterioration.

By replacing the deteriorated existing concrete slab with a new slab, it will be reborn as an Expressway that can be used safely and comfortably.

Construction overview

Image image of construction outline

5 Requests for use

  • [1] Face-to-face traffic will be restricted throughout the construction section for approximately 4.1 km. We are reducing the current two lanes from one lane to one lane, and we are forecasting long traffic congestion (up to about 20km on the In-bound line, up to about 12km on the Out-bound line), starting from the construction site. Please go out with a margin. Also, For customers who are planning to use the construction section on the day when heavy traffic congestion is predicted, for customers using the detour to Joban Expressway or the use of Expressway via general road , Please change the IC used or use public transportation.
  • [2] Since the driving lane and shoulder are narrow in the face-to-face traffic restricted section, observe the regulated speed when traveling, secure the distance between the vehicles, and pay sufficient attention to rear-end collisions. In addition, the lane changes greatly before and after the face-to-face traffic restricted section, so please follow the local information signs and so on.
  • [3] There are vehicles coming and going around the construction site, so please be careful and pass ahead.
  • [4] During the construction period, we will provide traffic congestion information and detour guidance using simple information boards, construction regulation information using road information boards and road signs, and call attention to drive safely. We will carry it out. Please check this information before riding and drive safely.

Image of information provision image around the construction site

Image of information provided around the construction site Image of a
Image image of information provided around the construction site Image image of b
Image image of information provided around the construction site Image image of c
  • The photo shows information provided by the Tohoku Regional Head Office.

6 Efforts to minimize inconvenience to customers due to construction

Use of precast products for shortening the construction period and improving quality

The use of precast PC slabs has shortened the construction period and shortened the regulatory period as much as possible.

  • Precast is a product manufactured in advance at a factory, etc.

Strengthening of information provision

  • [1] Notification of traffic congestion transit time using a simple information board
    On general roads and Expressway, a simple information board will provide you with information about transit times and congestion lengths, so please use it to select your route.
    • Simple information board display image
      Image of simple information board display
          
  • [2] Notification of latest traffic congestion information and detour guidance at rest facilities
    Expressway We will provide the latest traffic jam information of the construction section with a simple information board etc. at the following rest facilities. We will guide you from about 3 km before the rest facility that provides information, so please visit the rest facility and check the congestion information and detours.
    • A rest facility that provides traffic jam information
      Image of rest facility providing traffic jam information
      Image image of information provision rest facility
      • Simple information board installation image
        Image of simple information board installation image
        * A simple information board is installed near the toilet at each rest facility where information is provided.
    • Simple information board display image
      [1] Image of stop-off guide information image for rest facilities
      [1] Image of providing information on how to stop at a rest facility
      [2] Image of the image of providing traffic information in the rest facility
      [2] Image of providing traffic congestion information within the rest facility
  • [3] Advance notification of construction regulations and traffic congestion information through TV commercials, radio commercials, newspaper advertisements, etc.
    We will inform you in advance about the regulations by TV commercials, radio commercials and newspaper advertisements, mainly in the Tohoku region.

Information image * Publicity material for the renewal work that was carried out in the spring of 2018

Image image of TV commercial
TV commercial
Image of standing sign
Standing sign
Image image of poster
Posters
Image image of leaflet
Leaflet

7 How to Obtain Road Traffic Information

(1) Road traffic information available before going out
  • NEXCO EAST Website "Construction regulation information (Provides information on construction regulations in each area)
    For Fukushima Prefecture, please see "South Tohoku".
  • NEXCO EAST Road Traffic Information Site "Doratara" (Provide highway traffic information nationwide)
    [PC]
    [Mobile] http://m.drivetraffic.jp/
  • ハイウェイテレホン
    5分毎に更新される高速道路の交通最新情報をハイウェイテレホン(自動音声)で24時間提供しています。
    郡山局 024-961-1620
    (携帯電話・PHS短縮ダイヤル#8162
  • NEXCO東日本お客さまセンター(24時間オペレーターが対応します。)
    0570-024-024 または 03-5338-7524
  • (公財)日本道路交通情報センター(JARTIC)の道路交通情報
    050-3369-6761(東北地方・高速情報)
    インターネット
(2) Road traffic information available during driving
  • Road information board
  • Highway radio (AM1620kHz)
    Highway radio sections are indicated by signs on the Expressway.
  • Highway Information Terminal
    Wide-area road traffic information is reported on the monitor screens installed at SA and PA.
  • * Twitter's official account "NEXCO EAST (Tohoku)" (@e_nexco_tohoku ) Also delivers information.

Image of Renewal

Expressway renewal project

Now, bring safety and security to the next generation.
NEXCO EAST will work on updating and repairing highways to deliver safety and security to everyone.

Image link (external link) to download page of Adobe Acrobat Reader

To view the PDF file, you need the Adobe Systems plug-in software "Acrobat Reader (Japanese version)". If you do not have​​​ Download from here (free)Please use it.