[E4] Tohoku Expressway and [E49] Ban-Etsu Expressway
Notice of planned renovation work

  • Corporate Top
  • Press Room
  • Press Release Tohoku office
  • Notice of scheduled renewal construction on the [E4] Tohoku Expressway and the [E49] Ban-Etsu Expressway

The latest regulatory information isDraTraPlease see.

PDF version [PDF: 968KB]

Expressway renewal project logo image image 1

July 18, 2020
East Nippon Expressway Co., Ltd.
Tohoku Regional Head Office
Kanto Regional Head Office

NEXCO EAST Tohoku Regional Head Office (Sendai City, Miyagi Prefecture) and Kanto Regional Head Office (Saitama City, Saitama Prefecture) E4 Tohoku Expressway (hereinafter referred to as "Tohoku Expressway") and E49 We would like to inform you about Expressway renewal construction work that will begin on Ban-Etsu Expressway (hereinafter referred to as the "Ban-Etsu Expressway") from August 2025 onwards.
Please note that the number of lanes will be reduced due to the following traffic regulations.
The renewal work is necessary to ensure that customers can use Expressway safely and securely. We will do our best to minimize the inconvenience to our customers, so we ask for your understanding and cooperation.

1. Location map/traffic regulation schedule

Image of position map
number section Regulation form period Congestion Forecast Details
A Nango IC to Hachinohe JCT
(Up and Down Lines)
All-day traffic regulation April 14th - November 6th None
B Karumai IC to Nango IC
(Up and Down Lines)
All-day traffic regulation June 9th - October 16th None
C Joboji IC - Ichinohe IC
(up and down lines)
All-day traffic regulation April 3rd - October 29th None
D Kazuno Hachimantai IC to Kosaka IC
(both inbound and outbound lines)
All-day traffic regulation May 8th - September 28th None
E Hiraizumi Maesawa IC-Mizusawa IC
(Up and down line)
All-day traffic regulation August 26th - November 14th Focusing on holidays
Up to about 5km
Attachment-1 [PDF: 234KB]
F Ichinoseki IC to Hiraizumi Maesawa IC
(Both up and down lines)
All-day traffic regulation September 1st to November 14th Focusing on holidays
Up to about 5km
Attachment 2 [PDF: 189KB]
G Sendai Miyagi IC - Tomiya JCT
(Up and Down Lines)
All-day traffic regulation November 4th - December 15th centered around holidays
Up to over 5km
Attachment-3 [PDF: 364KB]
H. Shiroishi IC to Murata IC
(Both up and down lines)
All-day traffic regulation October 14th - December 15th centered around holidays
Up to over 5km
Attachment-4 [PDF: 388KB]
I Kunimi IC to Shiroishi IC
(In-bound line)
All-day traffic regulation September 1st to December 5th centered around holidays
Up to over 5km
Attachment-5 [PDF: 339KB]
J Motomiya IC - Nihonmatsu IC
(up and down lines)
All-day traffic regulation June 16th - December 19th None
K Bandai Atami IC to Bandai Kawahigashi IC
(Both up and down lines)
All-day traffic regulation August 18th - November 14th centered around holidays
Up to over 5km
Attachment-6 [PDF: 370KB]
L Iwaki Sanwa IC to Ono IC
(Up and Down Lines)
All-day traffic regulation August 19th - November 21st None Attachment-7 [PDF: 193KB]
M Nasu IC - Shirakawa IC
(up and down lines)
All-day traffic regulation September 1st to December 2nd centered around holidays
Up to over 5km
Attachment-8 [PDF: 420KB]

2. Construction details

All of the construction we will inform you about this time is floor slab replacement work. In this work, the concrete floor slabs that have been damaged due to deterioration and the increase in the number of large vehicles will be replaced with new, more durable prestressed concrete slabs. In addition, high-performance floor slab waterproofing is applied to the waterproof layer to prevent deterioration of the floor slab.

Image of construction content

Construction image photograph

[Surface traffic regulation status] photo
[Restrictions on face-to-face traffic]
[Old floor slab removal status] photo
[Removal of old slabs]
[New floor slab installation status] photo
[New slab installation status]

3. Requests when using

  1. The construction section will be closed to traffic throughout the day. In some sections, traffic congestion is predicted starting at the construction site, so please leave with plenty of time to spare.
  2. Since the lanes and road shoulders are narrow, please observe the speed limit when driving, secure a distance between vehicles, and be careful of rear-end collisions. In addition, lanes will change significantly before and after the restricted section, so please follow the local guidance signs.
  3. Vehicles for construction work may enter and leave the area around the construction site, so please be careful when traveling ahead.
  4. During the construction period, we will provide traffic congestion information using LED information boards, provide construction regulation information using road information boards and road signs, and call attention to driving safely. Please check this information before driving and drive safely.

Image of information provision image around the construction site

[LED information board] photo
[LED information board]
[Road information board] photo
[Road information board]
[Construction control material] photo
[Construction regulation materials]

Four. Requests when passing special vehicles

Due to this traffic regulation, special vehicles over 3.0m wide will not be able to pass through during the all-day traffic regulation period. Customers who wish to use the road are asked to take a detour to nearby roads.
In addition, please note that if a special vehicle permission (※1) has only been obtained for Expressway routes, you will also need to obtain permission for general roads.

  1. What is a special vehicle permit?
    This is a permit required by the Road Act and the Vehicle Restrictions Act for special vehicles that exceed general restrictions (length, weight, width, etc.) to travel on public roads.

5. How to obtain Expressway information

Expressway renewal project logo image image 2

Expressway renewal project
Now, safety and security to the next generation.
In order to deliver safety and security to everyone, NEXCO EAST will work on large-scale renewal and repair projects for Expressway.
Or search for "Fast Renewal".

The NEXCO EAST Group has positioned the period from 2021 to 2025 as "a period that contributes to the achievement of the SDGs and transforms into a new future society," and is making various efforts.
We believe that this "renewal work" initiative will contribute to the SDGs goals No. 8, 9, and 11 as business activities that lead to the development of safe, secure, and reliable infrastructure.

Image image of the SUSTAINABLE DEVELOPMENT GOALS logo and the 8th, 9th, and 11th logos of the SDGs target